skip to main content
Back to all blog posts

Posted in: Practice & Procedure | Facilities | Energy Policy | Climate Change / Renewables | British Columbia

Sep 22, 2017

BCUC’s Preliminary Report About Site C Reaches Few Conclusions

By David Stevens

On September 20, 2017, the British Columbia Utilities Commission (BCUC) issued its Preliminary Report about BC Hydro’s “Site C” hydroelectric project. This is the final step in the “fact gathering” phase of the Government-ordered “Site C Inquiry Process.” That process requires the BCUC to determine the implications of completing, suspending or terminating the Site C project. In the Preliminary Report, the BCUC indicates that the project is currently on schedule, but that it requires further information to determine whether the project is on budget and about the costs of suspending or cancelling and replacing the project. BC Hydro is required to provide this information by October 5 to ensure that the BCUC can issue its Final Report by November 1.

Background

As explained in the Preliminary Report, Site C is a dam and hydroelectric generating station being built by BC Hydro in the province’s northeastern Peace River Regional District. The project includes a new reservoir that will run 83 km along the Peace River and will submerge approximately 5,000 hectares of land. Site C is planned to provide a peak capacity of about 1,145 megawatts (MW) which, according to BC Hydro, will power the equivalent of 450,000 homes per year. The budget for the project is around $8.3 billion.

The Site C project received BC and Federal environmental approvals by November 2014 and construction began in the summer of 2015. The project was an issue in the recent provincial election, with the NDP and Green parties indicating that they would review and/or cancel the project if elected. After NDP leader John Horgan became Premier, an Order in Council (OIC) was issued requesting that the BCUC convene an inquiry. The OIC asked the BCUC to advise Cabinet on the implications of:

(i) completing the Site C project by 2024, as currently planned;

(ii) suspending the Site C project, while maintaining the option to resume construction until 2024; and

(iii) terminating construction and remediating the site.

The OIC also directed that the BCUC address specific questions, including whether the project is on time and on budget, what the costs are to suspend or cancel the project (and how could those costs be recovered) and what other options exist to meet the supply and clean energy benefits expected from the project.

The BCUC Inquiry Process

The OIC set an aggressive timetable for the BCUC inquiry, as can be seen in the diagram below (taken from the BCUC’s Site C Inquiry Webpage):

Fact Gathering

As can be seen, the Site C inquiry process is split into two phases: initial fact gathering which concluded with the publication of the Preliminary Report, and additional fact gathering, consultation and submissions concluding with the publication of a Final Report.

During the initial fact gathering phase, the BCUC sought submissions (including from BC Hydro), reviewed and analyzed those submissions, and engaged an expert to assist in estimating costs and identifying and evaluating alternatives to Site C.

The BCUC Panel assigned to the inquiry considered all submissions received, and then issued the Preliminary Report. As summarized in the BCUC Press Release dated September 21, the preliminary findings of the BCUC Panel included the following:

  • the Site C project is on time for an in-service date of November 2024;
  • the cost to terminate the project and remediate the site would be $1.1 billion (in addition to the $1.8 billion spent to date), but there would be further costs required to replace the needed energy that would have been produced by Site C; and
  • there is not currently clear information about the total costs for the project in the event it is suspended and restarted at a later date.

Importantly, the BCUC Panel identified further information that it needs in order to make findings on a number of required items, including whether the project is currently on budget, the cost to BC Hydro ratepayers of continuing, suspending or terminating Site C, and what the reasonable alternatives to the project are. BC Hydro has been directed to file additional information addressing 70 specific follow-up questions to be completed by October 4.

Next Steps

In addition to receiving and reviewing the additional requested information from BC Hydro, the BCUC has invited submissions from BC Hydro and the public to be provided by October 11, and also plans to conduct an “extensive consultation process” on its preliminary findings. As explained on the Site C Inquiry Webpage, the BCUC will hold “Community Input Sessions … in all major population centres in BC and in areas where the Panel considers the Site C project has a higher impact.” Input will also be sought from First Nations.

As required by the OIC, the BCUC will issue its Final Report on November 1. 


Areas of Expertise

Related Blogs

Saskatchewan Challenges Ottawa’s Proposed Carbon Tax By David Stevens Apr 26, 2018 On April 25, 2018, the Saskatchewan government announced that it has commenced a “reference case” to the Saskatchewan Court of Appeal, asking for a determination about whether the federal carbon levy will be "unconstitutional, in whole or in part." This is part of the effort of the Saskatchewan g...

Posted in: Practice & Procedure | Ontario | Facilities

Insights EnergyInsider
OEB Selects EPCOR to Provide Gas Distribution Service to South Bruce Municipalities By David Stevens Apr 20, 2018 On April 12, 2018, the Ontario Energy Board issued a Decision and Order in a proceeding to select a gas distributor to serve South Bruce municipalities (Municipality of Arran-Elderslie, the Municipality of Kincardine and the Township of Huron-Kinloss). The OEB chose EPCOR Southern Bruce Gas Inc.,...

Posted in: Practice & Procedure | Ontario | Ratemaking | Energy Policy

Insights EnergyInsider
OEB Rejects Hydro One’s Proposed Acquisition of Orillia Power Distribution By David Stevens Apr 18, 2018 On April 12, 2018, the Ontario Energy Board issued a Decision and Order denying Hydro One Inc.’s application to purchase the shares of Orillia Power Distribution Corporation. The OEB’s Decision explains that Hydro One and Orillia Power have failed to establish that there will be no harm to Orilli...