skip to main content
Back to all blog posts

Posted in: Ontario | Practice & Procedure | Facilities | Consumer Protection

Apr 13, 2017

OEB Requires Electricity Distributor to Take Over Embedded Distributor's Operations

By David Stevens

On April 4, 2017, the Ontario Energy Board (OEB) issued an Order requiring Algoma Power Inc. (Algoma Power) to operate the electricity distribution system owned by Dubreuil Lumber Inc. (DLI) in the Township of Dubreuil (which is north of Wawa, Ontario). The OEB's Order follows notification from DLI that it would not be able to continue to offer electricity distribution service to its 300 customers because of financial and staffing issues.

Under the OEB's Order, Algoma Power is granted a six-month interim distribution licence to take possession and control of the DLI electricity distribution system and provide service to and collect revenues from DLI's customers. Algoma Power is required to report to the OEB about the condition of DLI's distribution system and to record both revenues and costs from serving DLI's customers in a deferral account. In the meantime, DLI is required to either renew its distribution licence or sell or transfer its distribution assets to another licensed distributor.

The OEB's Order relies on section 59 of the OEB Act, which allows the OEB to issue an interim licence authorizing a distributor to take possession and control of the business of another distributor where the other distributor has failed or is likely to fail in meeting its obligations to serve. This provision is meant to be used in emergencies to ensure continuity of service to customers while arrangements are made for the resumption or formal transfer/sale of the incumbent distributor's operations.

Section 59 of the OEB Act has also been used to require Hydro One Networks Inc. to remain in possession and control of the distribution assets of Cat Lake Power Utility Ltd. and to serve its customers. As seen in the Decisions related to Cat Lake, the interim licence to Hydro One has been in place for more than 10 years (though it is expected that at some point Hydro One Remote Communities will file a MAADs application to acquire the Cat Lake Power assets).

Related Blogs

Posted in: Ontario | Practice & Procedure | Ratemaking | Facilities

Insights EnergyInsider
OEB Issues Its Largest Rate Case Decision Ever By David Stevens Jan 18, 2018 On December 28, 2017, the Ontario Energy Board (OEB) issued its Decision with Reasons in the Ontario Power Generation “Payment Amounts” case, covering the 2017 to 2021 period. Among the notable determinations are an approval of the forecast costs of the Darlington Refurbishment Project and reduct...

Posted in: Ontario | Practice & Procedure | Facilities

Insights EnergyInsider
Ontario Court of Appeal Finds That Gas Utility’s Franchise Agreement Prevails Over Drainage Act By David Stevens Jan 16, 2018 In a decision released on January 10, 2018, the Ontario Court of Appeal found in favour of Union Gas on the question of whether the cost sharing provisions of a model franchise agreement apply to the relocation of a gas pipeline necessitated by drainage works. The Court found that the provisions ...

Posted in: Utility Mergers | Ratemaking | Practice & Procedure | Ontario

Insights EnergyInsider
OEB Allows Review Motions in Hydro One/Orillia Power Proceeding By Fred D. Cass Jan 10, 2018 In August 2017, we wrote about a Procedural Order issued by the Ontario Energy Board in which the OEB adjourned the hearing of an application (“MAADs” application) by Hydro One Inc. for approval to acquire Orillia Power Distribution Corporation until a decision on Hydro One’s distribution rate ap...