skip to main content
Back to all blog posts

Posted in: Practice & Procedure | Facilities | Energy Policy | Climate Change / Renewables | British Columbia

Sep 22, 2017

BCUC’s Preliminary Report About Site C Reaches Few Conclusions

By David Stevens

On September 20, 2017, the British Columbia Utilities Commission (BCUC) issued its Preliminary Report about BC Hydro’s “Site C” hydroelectric project. This is the final step in the “fact gathering” phase of the Government-ordered “Site C Inquiry Process.” That process requires the BCUC to determine the implications of completing, suspending or terminating the Site C project. In the Preliminary Report, the BCUC indicates that the project is currently on schedule, but that it requires further information to determine whether the project is on budget and about the costs of suspending or cancelling and replacing the project. BC Hydro is required to provide this information by October 5 to ensure that the BCUC can issue its Final Report by November 1.

Background

As explained in the Preliminary Report, Site C is a dam and hydroelectric generating station being built by BC Hydro in the province’s northeastern Peace River Regional District. The project includes a new reservoir that will run 83 km along the Peace River and will submerge approximately 5,000 hectares of land. Site C is planned to provide a peak capacity of about 1,145 megawatts (MW) which, according to BC Hydro, will power the equivalent of 450,000 homes per year. The budget for the project is around $8.3 billion.

The Site C project received BC and Federal environmental approvals by November 2014 and construction began in the summer of 2015. The project was an issue in the recent provincial election, with the NDP and Green parties indicating that they would review and/or cancel the project if elected. After NDP leader John Horgan became Premier, an Order in Council (OIC) was issued requesting that the BCUC convene an inquiry. The OIC asked the BCUC to advise Cabinet on the implications of:

(i) completing the Site C project by 2024, as currently planned;

(ii) suspending the Site C project, while maintaining the option to resume construction until 2024; and

(iii) terminating construction and remediating the site.

The OIC also directed that the BCUC address specific questions, including whether the project is on time and on budget, what the costs are to suspend or cancel the project (and how could those costs be recovered) and what other options exist to meet the supply and clean energy benefits expected from the project.

The BCUC Inquiry Process

The OIC set an aggressive timetable for the BCUC inquiry, as can be seen in the diagram below (taken from the BCUC’s Site C Inquiry Webpage):

Fact Gathering

As can be seen, the Site C inquiry process is split into two phases: initial fact gathering which concluded with the publication of the Preliminary Report, and additional fact gathering, consultation and submissions concluding with the publication of a Final Report.

During the initial fact gathering phase, the BCUC sought submissions (including from BC Hydro), reviewed and analyzed those submissions, and engaged an expert to assist in estimating costs and identifying and evaluating alternatives to Site C.

The BCUC Panel assigned to the inquiry considered all submissions received, and then issued the Preliminary Report. As summarized in the BCUC Press Release dated September 21, the preliminary findings of the BCUC Panel included the following:

  • the Site C project is on time for an in-service date of November 2024;
  • the cost to terminate the project and remediate the site would be $1.1 billion (in addition to the $1.8 billion spent to date), but there would be further costs required to replace the needed energy that would have been produced by Site C; and
  • there is not currently clear information about the total costs for the project in the event it is suspended and restarted at a later date.

Importantly, the BCUC Panel identified further information that it needs in order to make findings on a number of required items, including whether the project is currently on budget, the cost to BC Hydro ratepayers of continuing, suspending or terminating Site C, and what the reasonable alternatives to the project are. BC Hydro has been directed to file additional information addressing 70 specific follow-up questions to be completed by October 4.

Next Steps

In addition to receiving and reviewing the additional requested information from BC Hydro, the BCUC has invited submissions from BC Hydro and the public to be provided by October 11, and also plans to conduct an “extensive consultation process” on its preliminary findings. As explained on the Site C Inquiry Webpage, the BCUC will hold “Community Input Sessions … in all major population centres in BC and in areas where the Panel considers the Site C project has a higher impact.” Input will also be sought from First Nations.

As required by the OIC, the BCUC will issue its Final Report on November 1. 


Areas of Expertise

Related Blogs

Posted in: Climate Change / Renewables | Ontario | Practice & Procedure

Insights EnergyInsider
Sell-Out in Final California/Quebec Carbon Allowances Auction Before Ontario Joins By David Stevens Nov 24, 2017 The results from the November 14, 2017, California and Quebec joint auction of greenhouse gas (GHG) allowances were released on November 22, 2017. All available current and future vintage allowances from both Quebec and California were sold at the latest auction. As we have described in previous ...

Posted in: Ontario | Practice & Procedure | Consumer Protection

Insights EnergyInsider
OEB Again Bans Winter Disconnections of Residential Electricity Customers By David Stevens Nov 06, 2017 On November 2, 2017, the Ontario Energy Board (OEB) issued a Decision and Order amending the licences of electricity distributors to direct that residential customers may not be disconnected during the winter season. This follows a similar OEB direction last winter that was put into place after t...

Posted in: Facilities | Practice & Procedure | Canada (Federal)

Insights EnergyInsider
NEB Publishes Interactive Pipeline Incidents Tool By David Stevens Oct 26, 2017 Recently, the National Energy Board (NEB) published an interactive online tool that helps users access and review a wide range of information about pipeline incidents at NEB-regulated pipelines and facilities. This tool allows interested parties to find, compare, sort and review data about “repor...